Vision 2023 - Accommodating our Current & Future Growth
On behalf of the Jim Ned CISD Board of Trustees & administration, thank you for your support in passing Proposition A of the 2023 Bond Package. Proposition B, which was the additional funds needed to build the Jim Ned CISD Auditorium, did not pass in the 2023 Bond Election, so we have formed a Fine Arts Stakeholder Committee to help provide direction forward for how we can meet the needs of our JNCISD Fine Arts programs moving forward.
To our Jim Ned community, we want you to know the vision the board has for facility & program needs in the district, particularly as our enrollment continues to grow. The board developed this vision of our facility needs in a variety of board meetings & strategic planning sessions with our administrators & current partners in Jacob-Martin Architecture & Engineering firm as well as Collier Construction.
As a reminder to our community, the previous 2020 Bond of approximately $34 million dollars included 2 propositions: a) Proposition A included about $26 million & included the new 4th-6th Grade Intermediate School along with several other smaller projects. Of the smaller projects, due to serious cost escalation after the pandemic, we were only able to afford the MS classroom additions & MS Cafeteria. That, coupled with the new Intermediate consumed almost all of the $26 million dedicated to Prop A. b) Proposition B was $7.8 million towards a new Auditorium & we want our JN community to know that we still have that money. We chose not to sell the $7.8 million in bonds since we knew we could not build an 850 seat auditorium for $7.8 million in today's commercial construction market. But, in the 2023 Vision, the District intended to build an auditorium using the $7.8 million & then add $4.8 million in 2023 Bond Funds in the 2023 Proposition B. Proposition B of the 2023 Bond did NOT pass. Therefore, the District has developed a Fine Arts Stakeholder Committee to determine a path forward for Fine Arts.
Below represents a culmination of months of meetings & several discussions about various facilities needs in Jim Ned that spanned from March 2023 through August 2023. Mainly, thanks to the 2020 bond, our next relief valve that we anticipated for our ever-increasing enrollment is our High School. Current cost projections are included below for a total of $28 million forecasted for the 2023 Bond:
- As mentioned above, relief at both elementary schools & the middle school has arrived in the form of Jim Ned Intermediate (4th-6th grade) on Hwy 83! This campus opened in August 2023 & has generated space at the 3 campuses mentioned above. For several years, we should have adequate space at the new Intermediate;
- High School North Academic Addition. As we predicted, our biggest need right now is accommodating students & staff at our growing High School. The board will add 12 new classrooms, including 2 new science labs & a new Life Skills room for HS students, at a projected cost of $6,260,738;
- Fine Arts: Auditorium in Prop B = $4,862,217 (to be added to the $7.8 we still have from unspent 2020 Prop B bond funds). Proposition B of the 2023 Bond did NOT pass, but this needs remains in the District. We have formed a Fine Arts Stakeholder Committee to determine a path moving forward.
- Career Technical Education (CTE). Our community will remember approving this project in the 2020 bond. However, we had to cull this project due to the inflation in the construction market. A 10,000sf facility in today's dollars will cost about $5,384,016 & will house HS Ag Classes & other courses to be determined. Other courses will include a Medical/Health-related Course Pathway for HS students. The existing Ag building will then house Middle School CTE/Ag classes, focusing on woodworking.
- Ag Education: New Show Barn & Animal Barn = $1,000,000.
- Renovate & upgrade our Family & Consumer Science Classroom (formerly Home Economics back in the day) = $500,000
- Interior Hallway Improvements at JNHS = $1,008,776;
- HS Cafeteria Renovation = $600,000;
- Existing Restroom Renovations for All Restrooms at JNHS = $488,786
- Locker Room Addition (this project was also in the 2020 bond but was culled due to inflation) = $2.332,679;
- Campus Parking Lot Circulation Improvements = $1,462,562;
- New JNHS Entrance/Updated Elevations = $1,134,648;
- Parking Lot Expansion = $356,702
- Middle School: Parking Lot Improvements = $500,000
- Support Facilities: a) Demo Current Bus Barn & Show Barn = $217,229; b) Paving at Demo Site = $245,216; c) Build New Bus Barn Office, Wash Bays, & Fueling Station on 10 acres near softball field = $1,000,000.
- Intermediate School - Locker Room Addition: When the Intermediate School was being designed, we had to cut the Locker Rooms we had planned for 6th grade Pre-Athletics due to cost escalation in that building. The board sees a need to add Locker Rooms for our students to more fully utilize this facility & for us to accommodate volleyball & basketball tournaments as we had originally planned = $1,000,000.
The total costs of both propositions is $28,342, 491. However, only $23,480,274 was passed by voters in the 2023 Bond Election. This was Proposition A of the 2023 Bond Package. Our current bonding capacity is much higher than $28M, but the board only desired to meet our needs & not max out our tax rate. We know that our community appreciates that.
We will keep our community posted on facility needs as we move forward &, as always, we greatly appreciate your support of our Jim Ned students & staff! Roll Tribe!